Study Material for PMP Certification
Memory Aids - PMBOK 4th Edition - Part 2
Project Human Resource Management Overview
- 9.1 Develop Human Resource Plan - NOO
- N - Networking
- O - Organization charts & position descriptions
- O - Organizational theory
- 9.2 Acquire Project Team - Present NAV
- P - Pre-assignment
- N - Negotiation
- A - Acquisition
- V - Virtual team
- 9.3 Develop Project Team - Ground rules In Training & Team-building Reduce Controversies
- 9.4 Manage Project Team - PIO Card for Indians
- 10.1 Identify Stakeholders - Expert System
- E - Expert judgement
- S - Stakeholder analysis
- 10.2 Plan communications - Communication methods + Requirement Traceability Matrix
- R - Requirement analysis (Communication)
- T - Technology (Communication)
- M - Models (Communication)
- 10.3 Distribute Information - Communication method + Information distribution tools
- 10.4 Manage Stakeholder Expectations - Communication method + Instant Messenger
- I - Interpersonal skills
- M - Management skills
- 10.5 Report Performance - Communication method + Report for Variance & Forecasting
- R - Reporting system
- V - Variance analysis
- F - Forecasting methods
Memory Aids - PMBOK 4th Edition - Part 1
One of the changes done in PMBOK 4th edition is that all the processes names are changed to reflect the verb-noun format i.e. earlier if the process name was scope control, it is now changed to control scope, earlier if the process name was Human Resource Planning it is now changed to Develop Human Resource Plan. For more changes in PMBOK Guide 4th edition read this.
Below are some tips to memorize Tools & Techniques for PMBOK Guide 4th edition processes.
Project Time Management Overview
Below are some tips to memorize Tools & Techniques for PMBOK Guide 4th edition processes.
Project Time Management Overview
- 6.1 Define Activities - DRTE - Defence Research Telecommunication Establishments (a part of Canadian Defence Research Board)
- D - Decomposition
- R - Rolling Wave Planning
- T - Templates
- E - Expert Judgement
- 6.2 Sequence Activities - PADS
- P - Precedence diagramming method
- A - Applying leads & lags
- D - Dependency determination
- S - Schedule network templates
- 6.3 Estimate Activity Resources - BEAPP
- B - Bottom up estimating
- E - Expert judgement
- A - Alternatives analysis
- P - Published estimating data
- P - Project management software
- 6.4 Estimate Activity Durations - TAPER
- T - Three point estimates
- A - Analogous estimating
- P - Parametric estimating
- E - Expert judgement
- R - Reserve Analysis
- 6.5 Develop Schedule - SCC WARSS or Schedule may Change With Stakkeholder's Approved Scope ChangeRequest
- 6.6 Control Schedule - VPP WARSS
- 8.1 Plan Quality - CCB Decides Strategy For Changes
- 8.2 Perform Quality Assurance - PQ
- 8.3 Perform quality control - Sensors Help In detecting Fire And Cause Remote Sirens to Play Continously
Key Concept and Formulas for PMP Exam
| Key Concept and Formulas for PMP Exam | |
| Earn Value Formulas | |
| PV (Planned Value) = BCWS (Budgeted Cost of Work Scheduled EV (Earned Value) = BCWP (Budgeted Cost of Work Performed) AC (Actual Cost) = ACWP (Actual Cost of Work Performed) SV = EV – PV (minus is behind schedule) CV = EV – AC (minus is over budget) SPI = EV/PV (Less than 1 is behind schedule) CPI = EV/AC (Less than 1 is over budget) EAC = AC + (BAC-EV) Use when variances are atypical EAC = AC + [(BAC-EV)/CPI] Use when variances are typical (Note: This is the same as EAC = BAC/CPI) VAC = BAC – EAC ETC = BAC – EV Use when variances are atypical ETC = (BAC – EV)/CPI Use when variances are typical ETC = EAC – AC Use when original estimates were flawed | NPV (Net Present Value) = FV/(1+r)n FV= Future Value, r= interest rate, n= no. of time periods Higher NPV is better IRR (Internal Rate of Return) = Solve the NPV equation for “r” Also called Hurdle Rate Higher IRR percentage is better BCR (Benefit/Cost Ratio) Higher BCR is better. Beware, exam can call it CBR, where lower is better ROI (Return on Investment) = Earnings/Investment Higher ROI is better Payback Period = Time to recover cost of the project Lower payback period is better Cash Flow = Cash In – Cash Out |
| Network Diagram | Calculating Stackor Float |
Precedence Diagramming Method (PDM)
Arrow Diagramming Method (ADM)
Graphical Evaluation and Review Technique (GERT)
| Total Float (also called Slack, Float, or Project Float) is the total amount of time an activity can be delayed without delaying the project finish date. Free Float/Slack is the amount of time an activity can be delayed without delaying its successor (following activity).
Lead Time: Overlapping activities, also called paralleling or fast tracking. “Lead In; Lag Out” |
Three Point Estimates, or PERT | |
PERT = PROGRAM Evaluation and Review Technique Holds schedule and lets cost float 3 estimates for each task: Optimistic, Pessimistic, and Most Likely Mean Estimate = (O + 4*ML + P)/6 Standard Deviation (s) = (P – O)/6 Variance = s2 , or [(P – O)/6]2 Standard deviation of tasks on CP = Sum of variances | Order of Magnitude:-25% to +75% Budget Estimate:-10% to +25% Definitive Estimate:-5% to +10% |
1. Expert: Best, earned on your own 2. Reward: Next best. Based on PM position 3. Formal: Power, based on PM position 4. Referent: Referring to positions of others 5. Penalty: Worst. Based on PM position | 1.Problem Solving: Also called Confronting 2. Compromising: Solutions satisfy both parties 3. Withdrawal: Postponing a decision 4. Smoothing: Emphasis on agreement 5. Forcing: One viewpoint at expense of another. |
Sources of Conflict (Order of Priority) | Herzberg’s Motivators |
1. Schedules 2. Project Priorities 3. Resources 4. Technical Opinions 5. Administrative Procedures 6. Cost 7. Personality | 1. Achievement 2. Recognition 3. Challenge of the work itself 4. Responsibility 5. Advancement 6. Growth |
Channels of Communication | Closing |
Between Team Members = N(N-1)/2 | Project is closed when administrative closure is complete. Administrative closure is done at end of each Project Phase and at the end of the Project. Contract closure: verification that deliverables were acceptable; it is done once at the end of the contract. Contract Closure Procedure is produced under “Close Project” |
Project Integration Framework– Terms and Concepts
| Important Terms and Concepts (Take printouts and Fold at the center to make Flashcards for quick reference) | ||
| 1 | Control Account | A management control point where the resource plans, scope, schedule and actual cost are integrated and compared to earned value for performance measurement. |
| 2 | Organizational Policies | Formal and informal policies that are required for project plan development. Organizational policies include quality management, personnel administration and financial controls. |
| 3 | Constraints | An applicable restriction that will affect the performance of the project/process. |
| 4 | Assumptions | Factors which, for planning purposes, are considered to be true, real or certain. |
| 5 | Project Planning Methodology | Structured method to guide the project team during development of project plan. Standard forms and templates or even complicated simulations may be used. |
| 6 | Project Management Information Systems (PMIS) | It consists of tools and techniques used to gather, integrate and disseminate the outputs of project management processes. Supports all aspects of the project from initiating through closing, and can include both manual and automated systems. |
| 7 | Project Plan | A formal, approved document used to define how the project is executed, controlled and monitored. It can either be at a detailed or high level and may contain one or more subsidiary plans. |
| 8 | Corrective Action | An accepted action performed to bring projected future project performance in line with the project plan. These actions have to be documented. |
| 9 | Work Authorization System | A formal procedure for authorizing project work to ensure that work is done by the identified organization at the right time and in proper sequence. |
| 11 | Status Review Meetings | Meetings that are regularly scheduled to exchange and analyze information about the project and its performance. |
| 12 | Work Results | Outcome of activities performed to accomplish the project. |
| 13 | Change Control System | A collection of formal (note: not informal) documented procedures, which defines how the documentation and project deliverables will be managed, changed and approved. |
| 15 | Configuration Management System | A group of documented procedure used to apply technical and administrative direction and surveillance to: a) Identify and document the system’s functional and physical characteristics b)Control any changes to such characteristics c) Record and report the change and its implementation status and d) Audit the items and systems to verify compliance to requirements |
| 20 | Project Plan Updates | Any modification to the contents of the project plan or the supporting details. |
| 21 | Lessons Learned | Specify lessons that can be learned from each and every project, even from projects which are failures. They need to be documented. Most companies prefer post-implementation meetings and case studies to document Lessons Learned |
Kathy Schwalbe 6e PPT
Subscribe to:
Posts (Atom)